Handing over your snag list is not the finish line, it’s the start of the real work. In our experience across new developments in Dublin and Wicklow, the next few weeks are where things either get sorted properly or quietly get buried under paint and silicone before you’ve a chance to check them. Don’t sign anything final until you’ve walked the house again with your own eyes, or ideally with a trade who isn’t on the builder’s payroll.
The snag list is a negotiation, not a guarantee
A lot of first-time buyers treat the snag list like a contract the builder is legally bound to complete item for item, in full, to a high standard. That’s not quite how it works in practice. The developer’s site team will generally work through the list, but they’ll prioritise what’s quick and cheap over what matters most to you, and some items will get marked “not a defect” even when they clearly are. We see this a lot on estates around Blessington and Kilcoole where the same snagging issues (uneven floor screeds, gaps around window reveals, poor external render finish) turn up across several houses on the same phase of a build.
What actually happens behind the scenes: the site foreman gets your list, assigns bits to whichever subcontractor did that trade originally (the plasterer, the electrician, the tiler), and they come back on a schedule that suits them, not you. If you’re not firm about timelines in writing, “we’ll get to it” can drift for months.
What should happen once you’ve submitted your snags
There’s a reasonable sequence most reputable builders follow, and it’s worth knowing it so you can spot when it’s slipping:
- Builder or site agent acknowledges the list in writing and gives a rough timeframe for each category of fix
- Trades are sent back to complete the work, usually the same subcontractors who did the original job
- You (or your engineer, or a trade you’ve brought in) re-inspect the completed fixes against the original list, item by item
- Anything still outstanding or badly fixed goes back on a revised list, not a new one buried at the bottom of an email chain
- Only once you’re satisfied should you sign any snag closure document or release retained funds if that applies to your contract
That last point matters more than people realise. Some contracts tie a final payment or deposit release to snag sign-off. Read what you’re actually signing before you sign it, and if you’re not sure what it commits you to, ask your solicitor rather than the site agent.
Fixes homeowners regret approving too quickly
The ones that catch people out are rarely the obvious cosmetic snags like a scuff on a skirting board. It’s the fixes that look fine from standing height but aren’t actually resolved underneath. A re-painted patch over a damp stain without the source of the damp being found. A re-pointed section of external wall where the real issue was poor flashing above it. A “levelled” floor that’s been skimmed rather than properly screeded, which just means the dip reappears once furniture goes on it.
In Dublin and Wicklow’s climate, anything involving water ingress, roof flashing, render, or external door and window seals deserves a harder look before you accept it as resolved. A lot of our new build stock, particularly the higher density schemes around Dun Laoghaire, Sandyford and Dublin city, has flat or low-pitch roof sections and exposed render finishes that are genuinely more vulnerable to wind-driven rain than older, more sheltered housing stock further inland. A fix that holds up fine in a dry spell can fail the first proper autumn storm.
What pushes the sign-off process out, and what speeds it up
Every new build sign-off runs at a different pace. The main things we see affecting how long it drags on are:
- Number and complexity of snags: a list heavy on structural or water-related items (roof, render, drainage) takes longer than one full of paint and door adjustment snags
- How many houses are ahead of yours: on a large phased estate, your subcontractor might be working through twenty other houses before yours
- Whether the original trade is still contracted: if the plasterer or roofer has moved on to another site or finished their contract, the builder may need to bring in someone else, which adds delay
- Weather: external work like render, pointing and roof flashing genuinely can’t be done properly in wet or frosty conditions, so winter handovers often take longer to close out
- How organised your own paperwork is: a clear, dated, photographed list with specific locations gets actioned faster than a vague verbal complaint
None of this is an exact figure, and anyone telling you a fixed number of weeks is guessing. What we can say from working on remedial jobs across these estates is that a tight, well-documented list closes out far faster than a loose one.
When to stop waiting on the builder and bring in your own trade
There’s a point, and it’s different for every build, where it’s not worth chasing the developer anymore. If a snag has gone unresolved past two or three follow-ups, if the “fix” has failed again, or if the issue is something you need sorted before you move furniture in or before winter, it’s often faster and less stressful to get an independent trade in to assess and quote the work directly. This is especially true for anything involving damp, drainage, or electrical snags where living with an unresolved issue isn’t really an option.
It’s also worth getting an independent opinion before you accept a fix as final, particularly on anything structural or water related. A second set of eyes that isn’t invested in closing out the builder’s snag list will tell you straight whether something’s actually sorted or just patched over.
We’ve worked on plenty of new build remedial jobs across Bray, Greystones, Arklow and the wider Dublin and Wicklow area, picking up exactly these kinds of unresolved snags once the builder’s warranty period attention has moved on. If you’re at that stage, our services page covers the trades we can send out, or you can go straight to get a quote for your specific job. You can also see more about how we work on our about us page, or get in touch through our contact page if you want to talk through what you’re dealing with first.
Frequently Asked Questions
How long should a builder take to fix snags after handover?
There’s no fixed legal timeframe that applies to every build, and it varies with the size of your list, the time of year, and how stretched the builder’s subcontractors are. A reasonable expectation is weeks rather than days for anything beyond minor cosmetic items, but if months pass with no movement, it’s time to escalate formally and consider independent advice.
Do I have to sign off on snags before I move in?
Not usually, and you shouldn’t feel pressured to. Snagging sign-off and handover are often separate processes, though some contracts link final payments to snag closure. Check your specific contract with your solicitor rather than relying on what the site agent tells you.
What if the builder says an item isn’t a defect?
This happens a lot, particularly around minor cracking, floor levels, or finish quality, where there’s a genuine grey area between “snag” and “normal settlement.” If you disagree, get an independent assessment from a trade or engineer who isn’t connected to the build, and keep the disagreement in writing rather than letting it go verbally.
Can I get my own trades in if the builder is too slow?
Yes, and in our experience it’s often the more practical route once a reasonable amount of time has passed with no real progress. Just check your contract or warranty terms first, as bringing in outside trades on certain structural items could affect any builder’s warranty still in place.
What new build defects are most common in Dublin and Wicklow?
From what we see on remedial jobs, water ingress around flat roofs and render, poor external door and window sealing, uneven floor screeds, and drainage or guttering issues that only show up in heavy rain are among the most frequent. The exposed, wet climate here means anything external gets tested hard within the first year or two.
Should I get an independent snag list done at all, or just rely on the builder’s own checks?
We’d always recommend an independent check rather than relying solely on the builder’s internal sign-off, since the people marking items as resolved are generally connected to the same company that built the house. It doesn’t need to be adversarial, it just gives you an honest second opinion before anything gets signed off as final.